From 10 months behind to profitable delivery
CST Unified Employee Portal
THE SITUATION
The CST Unified Employee Portal was designed to bring employee services from several legacy systems into one platform.
When I took responsibility for the project, it was already 10 months behind schedule and facing a projected SAR 2.5 million loss.
The problem was not only technical. The client, offshore development team, and two subcontractors responsible for Oracle and Remedy integrations were not operating as one delivery team. Progress was difficult to measure, responsibilities were unclear, and confidence in the project had been damaged.
WHAT I DID
I rebuilt the plan around achievable milestones and shorter delivery cycles.
Weekly demonstrations replaced long periods without visible progress. Executive reporting gave decision-makers a clearer view of risks, dependencies, and priorities.
I acted as the central connection between CST, the offshore developers, and the integration subcontractors. I clarified ownership, followed up on decisions, and made sure technical issues were addressed within the wider delivery plan.
THE RESULT
The portal was delivered on the revised timeline.
The projected SAR 2.5 million loss became a 10% net profit after tax.
The completed platform gave employees a more reliable single point of access to services that had previously been distributed across several systems.


- PROJECT RECOVERY
- 20+ PROFESSIONALS
- 10-MONTH DELAY RECOVERED
- 10% NET PROFIT